News

NFL plans to avoid Super Bowl power problems of ’13

NFL plans to avoid Super Bowl power problems of ’13

POWER PLAY: The 2013 Super Bowl was delayed for more than a half-hour due to power problems that left much of the stadium in the dark. Photo: Associated Press

EAST RUTHERFORD, N.J. (AP) — With the memory of last February’s Super Bowl power outage front and center, officials have laid out plans for how they plan to avoid a similar problem at MetLife Stadium in February.

The head of Public Service Electric & Gas says the utility is running a third power line into the electrical substation at the Meadowlands sports complex.

PSE&G president Ralph LaRossa said Thursday that even if two of the power lines fail, the third would be enough to power the complex.

LaRossa said the Super Bowl site will require about 18 megawatts of electricity, or about what it takes to power 12,000 homes.

A partial power outage that caused a 34-minute delay at the Superdome was blamed on an electrical relay device installed specifically to prevent a power failure.

Recent Headlines

in Music, Entertainment

Lorde curating ‘Hunger Games’ soundtrack

lorde

The 17-year-old pop star is recording a single for the third installment of the franchise.

in Entertainment

David Cassidy reportedly skips court for race track

cassidy

The '70s heartthrob was reportedly at the race track while his attorney was in court representing him on a drunken driving charge.

in Music

PHOTOS: Inside Michael Jackson’s Neverland Ranch

AP041217025232_18

Five years after the King of Pop's death, his iconic California home is about to be sold.

in Lifestyle

Adults embrace art, science sleepovers

museum

Kids have been sleeping overnight in museums across the country for years and now adults are getting in on the fun.

in Entertainment

Stars hold out for big payday on ‘Big Bang Theory’

bigbang

Production of the hit comedy is on hold as the show's stars demand big bucks.